Street Work in Lexington

Lexington Public Works crews are scheduled to mark and stripe certain streets in the city this week, mainly in the downtown area.
It’s expected that the city crews will work from midnight to 8:00 AM each day, in order to minimize disruptions to traffic and businesses. 
The work consists of painting center lines, stop lines, crosswalks, curbs, and parking spaces. 
Work on Washington Street will include marking out parking spaces and line markings in connection with the temporary detour route from the Nelson Street Bridge project.
Weather permitting, all of the work should be finished by May 24.