Friday, February 1, 2013

Bridge Project in Lexington



The contract has been signed between the Virginia Department of Transportation and Fairfield-Echols of Fishersville to build the new East Nelson Street Bridge in Lexington.
Nelson Street will be closed to through traffic starting Tuesday, February 5, around 9 a.m.
On the western side of the bridge, barricades will be placed on East Nelson St. at the approximate location of the end of the existing bridge. On the eastern side of the bridge, barricades will be placed to the west of Davidson Street which will stay open during construction. Varner Lane will be closed from Short Street to a point just beyond the northern side of the existing bridge. 
The new bridge is scheduled for completion mid-December 2013. 
Lexington officials say they encourage everyone to continue to come downtown for shopping, dining, and enjoyment. Parking is available and the detour around the bridge work should cause only minor inconveniences.